Article 1: Subject-matter and scope
Article 2: Definitions
Article 3: Certification of transmission system operators
When preparing the opinion referred to in the first subparagraph, the Commission may request the Agency to provide its opinion on the national regulatory authority’s decision. In such a case, the two-month period referred to in the first subparagraph shall be extended by two further months.
In the absence of an opinion by the Commission within the periods referred to in the first and second subparagraphs, the Commission shall be deemed not to raise objections to the regulatory authority’s decision.
Article 4: European network of transmission system operators for electricity
Article 5: Establishment of the ENTSO for Electricity
Article 6: Establishment of network codes
Where the Commission proposes to adopt a network code on its own initiative, the Commission shall consult the Agency, the ENTSO for Electricity and all relevant stakeholders in regard to the draft network code during a period of no less than two months. Those measures, designed to amend non-essential elements of this Regulation by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 23(2).
Article 7: Amendments of network codes
Article 8: Tasks of the ENTSO for Electricity
The Community-wide network development plan shall, in particular:
Article 9: Monitoring by the Agency
The Agency shall monitor the implementation by the ENTSO for Electricity of network codes elaborated under Article 8(2) and network codes which have been developed in accordance with Article 6(1) to (10) but which have not been adopted by the Commission under Article 6(11). Where the ENTSO for Electricity has failed to implement such network codes, the Agency shall request the ENTSO for Electricity to provide a duly reasoned explanation as to why it has failed to do so. The Agency shall inform the Commission of that explanation and provide its opinion thereon.
The Agency shall monitor and analyse the implementation of the network codes and the Guidelines adopted by the Commission as laid down in Article 6(11), and their effect on the harmonisation of applicable rules aimed at facilitating market integration as well as on non-discrimination, effective competition and the efficient functioning of the market, and report to the Commission.
Within two months from the day of receipt, the Agency shall provide a duly reasoned opinion as well as recommendations to the ENTSO for Electricity and to the Commission where it considers that the draft annual work programme or the draft Community-wide network development plan submitted by the ENTSO for Electricity do not contribute to non-discrimination, effective competition, the efficient functioning of the market or a sufficient level of cross-border interconnection open to third-party access.
Article 10: Consultations
Article 11: Costs
Article 12: Regional cooperation of transmission system operators
For that purpose, the Commission shall consult the Agency and the ENTSO for Electricity.
Article 13: Inter-transmission system operator compensation mechanism
The first period of time for which compensation payments shall be made shall be determined in the Guidelines referred to in Article 18.
Article 14: Charges for access to networks
Article 15: Provision of information
Article 16: General principles of congestion management
Except in cases of force majeure, market participants who have been allocated capacity shall be compensated for any curtailment.
The rest of revenues shall be placed on a separate internal account line until such time as it can be spent on the purposes set out in points (a) and/or (b) of the first subparagraph. The regulatory authority shall inform the Agency of the approval referred to in the second subparagraph.
Article 17: New interconnectors
Within two months from the date on which the request for exemption was received by the last of the regulatory authorities concerned, the Agency may submit an advisory opinion to those regulatory authorities which could provide a basis for their decision.
In deciding to grant an exemption, consideration shall be given, on a case-by-case basis, to the need to impose conditions regarding the duration of the exemption and non-discriminatory access to the interconnector. When deciding those conditions, account shall, in particular, be taken of additional capacity to be built or the modification of existing capacity, the time-frame of the project and national circumstances.
Before granting an exemption, the regulatory authorities of the Member States concerned shall decide upon the rules and mechanisms for management and allocation of capacity. Congestion-management rules shall include the obligation to offer unused capacity on the market and users of the facility shall be entitled to trade their contracted capacities on the secondary market. In the assessment of the criteria referred to in points (a), (b) and (f) of paragraph 1, the results of the capacity-allocation procedure shall be taken into account.
Where all the regulatory authorities concerned have reached agreement on the exemption decision within six months, they shall inform the Agency of that decision.
The exemption decision, including any conditions referred to in the second subparagraph of this paragraph, shall be duly reasoned and published.
When the requested information is not provided within the period set out in the request, the notification shall be deemed to be withdrawn unless, before the expiry of that period, either the period is extended by consent of both the Commission and the notifying bodies, or the notifying bodies, in a duly reasoned statement, inform the Commission that they consider the notification to be complete.
The notifying bodies shall comply with a Commission decision to amend or withdraw the exemption decision within one month and shall inform the Commission accordingly.
The Commission shall preserve the confidentiality of commercially sensitive information.
The Commission's approval of an exemption decision shall expire two years after the date of its adoption in the event that construction of the interconnector has not yet started by that date, and five years after the date of its adoption if the interconnector has not become operational by that date, unless the Commission decides that any delay is due to major obstacles beyond the control of the person to whom the exemption has been granted.
Article 18: Guidelines
The Guidelines shall make provision for appropriate and efficient harmonised locational signals at Community level.
Any such harmonisation shall not prevent Member States from applying mechanisms to ensure that network access charges borne by consumers (load) are comparable throughout their territory.
When adopting or amending Guidelines, the Commission shall:
Article 19: Regulatory authorities
Article 20: Provision of information and confidentiality
In particular, for the purposes of Article 13(4) and (6), regulatory authorities shall, on a regular basis, provide information on the actual costs incurred by national transmission system operators, as well as data and all relevant information relating to the physical flows in transmission system operators’ networks and the cost of the networks.
The Commission shall fix a reasonable time limit within which the information is to be provided, taking into account the complexity of the information required and the urgency with which the information is needed.
When sending a request for information to an undertaking, the Commission shall at the same time forward a copy of the request to the regulatory authorities of the Member State in whose territory the seat of the undertaking is situated.
The Commission shall, at the same time, send a copy of its decision to the regulatory authorities of the Member State within the territory of which the person is resident or the seat of the undertaking is situated.
The Commission shall not disclose information acquired pursuant to this Regulation of the kind covered by the obligation of professional secrecy.
Article 21: Right of Member States to provide for more detailed measures
Article 22: Penalties
In setting the amount of a fine, the Commission shall have regard to the gravity of the failure to comply with the requirements of the first subparagraph.
Article 23: Committee procedure
Article 24: Commission report
Article 25: Repeal
Article 26: Entry into force
It shall apply from 3 March 2011.
Recital 1
Recital 2
Recital 3
Recital 4
Recital 5
Recital 6
Recital 7
Recital 8
Recital 9
Recital 10
Recital 11
Recital 12
Recital 13
Recital 14
Recital 15
Recital 16
Recital 17
Recital 18
Recital 19
Recital 20
Recital 21
Recital 22
Recital 23
Recital 24
Recital 25
Recital 26
Recital 27
Recital 28
Recital 29
Recital 30
Recital 31
Footnote p0: This Regulation shall be binding in its entirety and directly applicable in all Member States.
Done at Brussels, 13 July 2009.